| | | First Proposal | First Proposal | Revised Proposal | Revised Proposal | | — Sandy Bond recent business school graduate who had recently been employed Huron

Accounting & FinancePayroll AccountingWorked Solution

Sandy Bond, a recent business school graduate who had recently been employed by Huron Automotive Company, was asked by Huron's president to review the company's present cost accounting procedures. In outlining this project to Bond, the president had expressed three concerns about the present system: (1) its adequacy for purposes of cost control, (2) its accuracy in arriving at the true cost of products, and (3) its usefulness in providing data to judge supervisors' performance.

Questions

1. Using the data in the exhibits, determine the cost of a 100-unit batch of model CS-29, a month's spare parts, and a month's work done for other divisions under the present method, Bond's first proposal, and Bond's revised proposal.

2. Are the cost differences among the methods significant? What causes these differences?

3. Suppose that Huron purchased a new machine costing $400,000 for the custom work department. Its expected useful life is five years. This machine would reduce machining time and result in higher quality custom carburetors. As a result, the department's direct labor-hours would be reduced by 30 percent, and this extra labor would be transferred to departments outside the carburetor division. About 10 percent of the custom work department's overhead is variable with respect to direct labor-hours. Using July's data:

a. Calculate the plantwide hourly rate (present method) if the new machine were acquired. Then calculate indicated costs for the custom work department in July, using both this new plantwide rate and the former $55.96 rate.

b. Calculate the hourly rate for the custom work department only (first proposed method), assuming the machine was acquired and the first proposed costing procedure was adopted. Then calculate indicated costs for the custom work department in July, using both this new rate and the former $55.96 rate.

c. Under the present costing procedures, what is the impact on the indicated costs of custom products if the new machine is acquired? What is this impact if the first proposed costing procedure is used? What inference do you then draw concerning the usefulness of the present and proposed methods?

4. Assume that producing a batch of 100 model CS-29 injectors requires 126 hours, distributed by department as shown in Exhibit 3, and $4,200 worth of materials. Huron sells these carburetors for $113 each. Should the CS-29 price be increased? Should the CS-29 be dropped from the product line? (Answer using both the present and the first proposed costing methods.)

5. Assume that Huron also offers a model CS-30 that is identical to a CS-29 in all important aspects, including price, but is preferred for some applications because of certain design features. Because of the CS-30's relatively low sales volume, Huron buys certain major components for the CS-30 rather than making them in-house. The total cost of materials and purchased parts for 100 units of model CS-30 is $8,000; the labor required per 100 units is 12, 7, 17, and 35 hours, respectively, in the casting/stamping, grinding, machining, and assembly departments. If a customer ordered 100 units and said that either model CS-29 or CS-30 would be acceptable, which model should Huron ship? Why? (Answer using only the first proposed costing method and the assumptions regarding CS-29 from question 4.)

6. What benefits, if any. do you see to Huron if either proposed costing method is adopted? Consider this question from the standpoint of (a) product pricing, (b) cost control, (c) inventory valuation, (d) charges to outside departments, (e) judging departmental performance, and (f) diagnostic uses of cost data. What do you conclude Huron should do regarding its costing procedures?

SOLUTION

Questions 1 and 2

Costing of a 100-unit batch of CS-29 carburetors:
First ProposalFirst ProposalRevised ProposalRevised Proposal
DepartmentHours(%)RateTotalRateTotalTotal
Casting/Stamping21(17)$52.97$1,112.37$53.12$1,115.52$1,115.52
Grinding12(10)48.14577.6846.75561.00561.00
Machining58(46)87.525,076.1686.505,017.005,017.00
Assembly35(28)40.191,406.6539.141,369.901,369.90
Total, proposed method126= 101% due to rounding8,172.868,063.428,063.42
Total, present method12655.967,050.9655.967,050.967,050.96
Difference$1,121.90(16% more)$1,012.46$1,012.46(14% more)

Indicated cost is higher under the proposed methods primarily because a CS-29 carburetor spends a higher-than-average proportion of time in the highest machining department and a less-than-average proportion in the low-cost assembly department. (Based on Exhibit 1, the “average” product spends 8%, 7%, 24%, 12%, and 49% of its time respectively in the five departments.

Costing of spare parts for inventory:
First ProposalFirst ProposalRevised ProposalRevised Proposal
DepartmentHours(%)RateTotalRateTotal
Casting/Stamping304(18)$52.97$16,102.88$53.12$16,148.48
Grinding270(16)48.1412,997.8046.7512,622.50
Machining1,115(66)87.5297,584.8086.5096,447.50
Total, proposed method1,689126,685.48125,218.48
Total, present method1,68955.9694,516.4455.9694,516.44
Difference$32,169.04(34% more)$30,702.04(32% more)

Indicated cost is higher under the proposed methods primarily because spares do not pass through the low-cost assembly department, and because they spend a higher-than-average proportion of time in the machining department.

Costing of work done for other divisions:
First ProposalFirst ProposalRevised ProposalRevised Proposal
DepartmentHours(%)RateTotalRateTotal
Casting/Stamping674(20)$52.97$ 35,701.78$53.12$ 35,802.88
Grinding540(16)48.1425,995.6046.7525,245.00
Machining2,158(64)87.52188,868.1686.50186,667.00
Total, proposed method3,372250,565.54247,714.88
Total, present method3,37255.96188,697.1255.96188,697.12
Difference$ 61,868.42(33% more)$ 59,017.76(31% more)

The difference in indicated cost arises for the same reasons as given above for spare parts.

The differences between the costs that result from the two proposed methods are not so great as the differences between the present method and either proposal. This is because the actual average overhead cost per hour in each department in July (Exhibit 2) did not differ greatly from the predetermined rates in Exhibit 4. The greatest difference in departmental actual versus predetermined rates is in assembly (5% higher actual than predetermined), which doesn’t enter into the calculations for spares or work for other divisions.

The machining department costs dominate all three calculations, and there is only 1.7% ($62.52 versus $61.50) difference in the overhead rates. Of course, whether the same would be true for months other than July depends on the variations in monthly volumes from the normal volume in those other months.

All three of these examples cited show that the present method gives lower costs than those under the proposed methods. However, it should be noted that some products are being overvalued by the present system. It is reasonable to assume that there are some products that require a relatively large amount of assembling time. Such products would, under the present system, be costed at more than their costs under the proposed systems.

Question 3

a. Plant as a single cost center:

Labor cost in custom work reduced by 30 percent$ 81,664* 30% = $24,499
Reduced labor cost for the plant:$ 658,448- 24,499 = $633,949
Overhead is:
Increased by new depreciation: $400,000/60 months =$ 6,667
Decreased by variable costs with reduced labor:
10% *$40.48 * 3,712 hours *30% =4,508
Net increase in overhead$2,159
Total overhead becomes $1,099,323 + $2,159 =$1,101,482
Total labor cost633,949
Total cost becomes$1,735,431
Total hours become 31,412 - (3,712*30%) = 30,298 hours
Plant-wide rate per hour is $1,735,431/30,298 hours = $57.28
Custom work costs if entire plant is treated as a single cost center:
Prior to new machine: 3,712 hrs. @ $55.96 =$207,724
After new machine: 2,598 hrs. @ $57.28 =148,813
Net decrease of 28%, or in total dollars =$ 58,911
b.Treating each department as a cost center:
Present overhead is $40.48 *3,712 hours =$150,262
Add: Additional overhead (net)2,159
New total custom work overhead$152,421
New total hours: 3,712 *70% = 2,598 hrs.
New hourly overhead rate: $152,421/2,598 =$ 58.67
Labor hourly rate22.00
New custom work hourly rate$ 80.67
Custom work costs using five cost center approach:
Prior to new machine: 3,712 hrs. @ $62.48 =$231,926
After new machine: 2,598 hrs. @ $80.67 =209,581
Net decrease of 9.6%, or in total dollars =$ 22,345
c.The calculations are shown above. If there is only one cost center, the purchase of a new machine results in a substantial decrease in the cost of custom carburetors and fuel injectors; whereas if there are five cost centers, the purchase of the machine results in significantly less change in the cost of items going through the custom work department. This is an interesting phenomenon. The proposed system reflects more accurately what has actually happened to costs. Furthermore, under the single cost center, an event in one department (such as the purchase of the machine in custom work) can have repercussions on the costs of other departments, and indeed can even affect the cost of products that do not pass through custom world
🔒

Unlock the complete assignment

You are viewing the free preview. Purchase this assignment once to reveal the complete resource.

$9.99 USD

Secure checkout is completed by Stripe.